Business & Operations Assessment

Findings, Recommendations, and 30/60/90-Day Plan

Prepared forAaron Honoré and Stuart Hicks
Prepared byBrittany Martin, Instar Partners
DateNovember 18, 2026

Start here

What I've Learned

Over the past two weeks, I've spent time learning how the business operates, what each of you is responsible for, and where you're running into problems that are making the work more difficult than it needs to be.

We've talked about the companies and divisions, construction and masonry projects, the people involved, how work gets from estimating to the field, and the financial records that are supposed to tell you how the business is performing.

Some areas will need more investigation as you implement this plan. But I have enough information to make recommendations about where I believe your time, attention, and resources should go over the next 90 days.

Three things have emerged as priorities:

1

Getting a reliable picture of the finances and establishing the processes to keep that information accurate.

2

Clarifying who is responsible for what, including the decisions people can make without involving Aaron or Stuart.

3

Documenting the project and administrative processes that are most important to the business.

Those are the three priorities Aaron identified when we started, and the assessment has reinforced all three.

What Happens First

I recommend beginning with five decisions:

From there, the detailed roadmap provides the next actions, proposed owners, dependencies, and completion criteria.

I've designed this assessment so the team can use it regardless of whether Instar is involved in the next phase.

Part One

Where things stand

Each finding opens with a click.

1

A $300 QuickBooks Charge

I think this is a useful example of what's happening more broadly.

During our November 13 meeting, Stuart told me about receiving a notice that a QuickBooks payment account had been deactivated.

After looking into it, he learned that the company had been paying for payroll-related functionality that, as far as he knew, hadn't been used. The charges had been coming through for months.

He'd seen the payments, but with two QuickBooks companies, he'd assumed they were part of the existing subscriptions.

I think this is a useful example of what's happening more broadly.

There are transactions occurring, bills being paid, projects moving, and people doing their jobs. But there's no consistent process for reviewing the full financial picture and making sure that what's happening in the bank accounts matches what the company believes is happening.

And that issue shows up in much more consequential places than a software subscription.

It shows up when we don't know whether a job has covered its overhead, when expenses aren't consistently connected to projects, when loan balances haven't been reconciled, or when we're trying to decide whether the business can afford another employee.

This is why I moved so quickly to help you identify accounting support.

2

The Three Priorities Aaron Identified

Financial management · Roles and responsibilities · Operating processes

During our November 4 kickoff, Aaron identified three things he wanted to accomplish over the next 90 days.

1

Financial management

Get QuickBooks, accounts payable, receivables, and financial reporting under control so the business has reliable information to make decisions.

2

Roles and responsibilities

Clarify what each person owns, where decisions are made, and what support is needed.

3

Operating processes

Document and improve the way construction and masonry projects move from initial opportunity through completion.

Aaron also described wanting more time to develop relationships, pursue opportunities, and grow the business, with an operating structure that doesn't require him to manage every detail.

I think we can make substantial progress on these goals over the next 90 days. Some of the accounting work may continue beyond that period, depending on what the bookkeeper finds.

3

What We Reviewed

This assessment is based primarily on conversations, available documents, and preliminary reviews.

During the assessment, we:

  • Met with Aaron and Stuart to understand the business, its history, and current operations.
  • Mapped the existing divisions, companies, and preliminary responsibilities.
  • Identified the systems being used and how information moves between them.
  • Walked through the construction and masonry project lifecycle.
  • Reviewed what financial information is currently available.
  • Interviewed two construction-experienced accounting providers and reviewed their proposals.
  • Identified areas requiring accounting, legal, insurance, or other professional review.
  • Began outlining the responsibilities and processes that need attention.

This assessment is based primarily on conversations, available documents, and preliminary reviews.

I haven't independently reconciled the financial accounts, verified legal structures, audited insurance coverage, or established the company's profitability. Those are important limitations, particularly when we get to decisions about staffing and spending.

Where the information is incomplete, I've identified what needs to be confirmed and who I recommend should address it.

4

What We Have to Work With

There's a substantial amount already in place.

There's a substantial amount already in place.

Honoré has longstanding construction experience, relationships that generate opportunities, people who understand the work, and systems that are already being used in different parts of the business.

The current operations include:

DivisionPrimary workCurrent leadership, as understood
General ConstructionCommercial, industrial, and some private constructionAaron and Stuart
Masonry & StuccoCommercial and industrial masonry, brick, block, and stuccoAaron, with field and administrative support
Disaster & Economic DevelopmentDisaster recovery, development, grant-related opportunities, and project managementNagib

The business also has QuickBooks, historical Sage records, Buildertrend, SharePoint, Microsoft Project, and Microsoft 365.

I'm interested in making better use of those tools before recommending that you purchase anything else.

The company has enough moving parts already. Adding software or creating elaborate procedures without understanding how the team will use them is likely to create more work.

5

Where I See the Most Immediate Problems

Seven areas, what we've learned, and what I recommend for each.

AreaWhat we've learnedWhat I recommend
Financial informationThe books are not current or reconciled enough for reliable management reportingPrioritize professional cleanup and establish current financial controls
Job profitabilityCosts are being recorded, but there's no consistent estimate-versus-actual reviewEstablish job-cost capture now, then test reporting on active projects
Financial administrationChecks, receipts, invoices, account connections, and supporting documents are handled inconsistentlyAssign ownership and establish standard procedures
ResponsibilitiesAaron and Stuart are carrying substantial overlapping operational workDocument the work and assign decision authority
Project handoffsImportant information moves between estimating, office administration, and field teams without consistently documented stepsEstablish a standard project kickoff and handoff process
SystemsSeveral systems contain different parts of the company's informationClarify which system owns which information
Future structureSeparate entities and expanded leadership responsibilities have been discussedReview with qualified advisors after establishing the financial picture

These are my priorities based on what I've learned so far. There are clearly things people are doing well, often through experience and relationships. I want to preserve those while reducing the number of things that depend on somebody remembering what to do.

6

Why Financial Work Comes First

Both of you are making decisions that would benefit from more reliable financial information.

Stuart currently spends a substantial amount of time managing projects, coordinating subcontractors and materials, handling billing, and trying to maintain accounting records.

Aaron is making business development, estimating, staffing, and major financial decisions.

Both of you are making decisions that would benefit from more reliable financial information.

For example, I can't responsibly recommend hiring another project manager without understanding what the business can afford, what current projects are contributing, and whether there's enough work to support that role.

I also wouldn't be comfortable recommending that you make a substantial investment in my services under those circumstances.

That means the next 30 days should be focused primarily on the financial work. We can continue identifying operational improvements and make changes that require little additional investment, but we should be careful about taking on new financial commitments until we understand the company's position.

7

Financial Cleanup and Financial Processes Need to Happen Together

The bookkeeper's work and the company's work should begin together.

You've selected a local bookkeeper to begin addressing the accounting work. I respect that decision, and the next step is making sure everyone understands what that engagement includes.

I recommend treating the financial work as two closely connected responsibilities.

The bookkeeper's work

Review historical records, reconcile accounts, address the balance sheet, establish the correct treatment of transactions, and produce reliable financial reports.

The company's work

Make sure new transactions are entered and documented properly, bills are approved, payments can be traced, receipts are retained, and expenses are associated with the correct jobs or overhead categories.

These activities should begin together.

We don't want the bookkeeper spending the next several months correcting historical records while the company continues generating new transactions that will eventually require the same work.

Part Two

The next 90 days

I would treat these as monthly areas of emphasis, rather than trying to complete everything before moving to the next one. There will be overlap, particularly between financial cleanup and operational improvements.

≡

My Recommended Sequence

Focus, financial work, operating work, leadership, and success for each 30 days.

First 30 daysDays 31–60Days 61–90
Primary focusFinancial cleanup and financial processesProject processes and responsibilityReporting, management, and future decisions
Financial workEstablish the bookkeeper's scope, account inventory, controls, and cash reviewContinue cleanup and improve job-cost captureBegin using reliable information to evaluate performance
Operating workClarify financial duties and immediate approvalsDocument and test priority workflowsReview adoption and identify remaining gaps
LeadershipIdentify decision responsibilitiesEstablish reporting and delegation routinesEvaluate staffing and operating structure
SuccessAccounting work is underway and current activity is being handled consistentlyPriority processes have owners and are being usedBetter information is available for the next set of decisions
Show tasks for:
Appendix A — First 30 Days: Financial Foundation
No tasks for this person in this phase.
10

The First 30 Days

Establish the financial processes the company needs while the local bookkeeper begins cleaning up the records.

Primary objective: Establish the financial processes the company needs while the local bookkeeper begins cleaning up the records.

The first month should accomplish five things:

  1. Get the bookkeeper properly engaged, with a written scope and reporting plan.
  2. Identify all accounts, financial records, and outstanding obligations.
  3. Establish clear responsibility for current financial transactions.
  4. Begin a weekly review of cash, upcoming payments, and collections.
  5. Confirm the plan for outstanding taxes and other financial or compliance issues.

The historical accounting cleanup may take longer than a month.

By day 30, we should at least understand the extent of the work, how it's being managed, what information will become available first, and what the team needs to do to prevent new problems.

11

Week One: Get the Bookkeeper Set Up Properly

Proposed leads: Stuart, with Aaron and the selected bookkeeper

Proposed leads: Stuart, with Aaron and the selected bookkeeper

I recommend beginning with one working meeting to establish the engagement and identify everything the bookkeeper will need.

The bookkeeper should have appropriate access to:

I would also ask the bookkeeper to provide a written scope that identifies the accounting periods being reviewed, the expected deliverables, what is excluded, and when management can expect the first useful reports.

Week-one result: A complete account inventory, approved access, an accounting cleanup plan, and a clear division of responsibilities.

12

Questions I Would Ask the Bookkeeper

Historical accounting · 2025 taxes · Current operations · Reporting · Cost and communication

Since I haven't interviewed the bookkeeper you've selected, there are several things I would want to establish before assuming the engagement covers everything the company needs.

Historical accounting

Does the engagement include both companies, the historical Sage records, bank and credit card reconciliations, loans, fixed assets, intercompany activity, and outstanding receivables and payables?

2025 taxes

Who will prepare and file the outstanding returns? What cleanup is necessary before those returns can be filed?

Current operations

Will the bookkeeper help determine how the team should enter transactions, retain documentation, assign job costs, and manage financial reviews?

Reporting

What reports will be delivered? When can the company expect a reliable balance sheet, profit and loss statement, and overhead picture?

Cost and communication

What work is included in the agreed fee, what could cost more, how will additional work be authorized, and how frequently will Stuart receive updates?

I would encourage you to get these answers in writing.

13

Financial Processes to Establish Immediately

Eight activities and what needs to be decided for each.

I recommend establishing a minimum set of financial procedures during the first two weeks.

ActivityWhat needs to be decided
Incoming vendor invoicesWhere are they received, who enters them, and who approves them?
Checks and paymentsWho can approve payments, and where is the supporting documentation retained?
Credit card purchasesHow are receipts submitted and how is the correct job or overhead category identified?
Job costsWhat information must accompany each material, labor, equipment, or subcontractor expense?
Customer billingWho prepares invoices and pay applications, verifies them, and tracks payment?
CollectionsWho follows up on unpaid balances and how are collection issues escalated?
Bank accountsWho reviews activity and confirms all accounts are represented in the books?
Intercompany activityWho documents transfers and ensures the bookkeeper can classify them correctly?

Stuart and Mauri are the logical people to begin this work with, although we should confirm their responsibilities and the bookkeeper's role before making anything permanent.

Deliverable: One financial responsibility guide that the team can actually follow.

14

Establish a Weekly Cash Review

A rolling 13-week cash-flow forecast. Proposed owner: Stuart, supported by Mauri and the bookkeeper.

We discussed the need for reliable financial reporting, and I think cash visibility is one of the first things Aaron and Stuart should begin using.

I recommend starting a rolling 13-week cash-flow forecast, even while the accounting cleanup is underway.

It should show:

  • Available cash by account, with the date and reliability of those balances identified.
  • Customer payments expected and when they're likely to arrive.
  • Payroll, subcontractor, material, and operating expenses.
  • Loan payments and recurring obligations.
  • Known tax and legacy commitments.
  • Potential shortfalls or decisions that need to be addressed.

This will be a working management tool. Early versions will contain estimates and will need to be corrected as the bookkeeper verifies records.

The point is to begin looking ahead consistently, particularly when deciding which obligations can be paid, which payments need follow-up, and whether the company has the resources to take on additional commitments.

Proposed owner: Stuart, supported by Mauri and the bookkeeper.

15

The First Month's Financial Review

Seven questions for Aaron, Stuart, and the bookkeeper at day 30.

At the end of 30 days, I recommend that Aaron, Stuart, and the bookkeeper meet to review what has been completed and what remains.

I would want answers to the following:

This meeting should establish the next accounting milestones and determine whether we can begin relying on any of the financial information for management decisions.

Appendix B — Days 31–60: Responsibilities and Processes
No tasks for this person in this phase.
16

The Second 30 Days

The initial priority should be the construction and masonry project lifecycle.

By the second month, I would expect the financial cleanup to remain underway, with the team beginning to use the financial procedures established during month one.

This is when I'd recommend spending more attention on the operating processes we've discussed.

The initial priority should be the construction and masonry project lifecycle.

The company already has ways of estimating, winning, preparing, managing, billing, and closing out jobs. I want to review those existing methods and establish the most important handoffs, required information, and assigned responsibilities.

I would begin with a small number of processes and test them on current work before documenting everything else.

17

Process Priority: Estimating Through Project Kickoff

Proposed lead: Aaron, with Stuart and estimating/administrative support

Proposed lead: Aaron, with Stuart and estimating/administrative support

The first process I'd document is how an opportunity moves from an invitation to bid to an active job.

That includes:

  1. Receiving and evaluating the opportunity.
  2. Deciding whether to bid.
  3. Preparing estimates and supporting assumptions.
  4. Reviewing and approving the proposal.
  5. Executing the contract.
  6. Assigning the project owner.
  7. Transferring the estimate, scope, schedule, and required documents.
  8. Confirming the field team has what it needs to begin.

We discussed existing proposal templates, SharePoint job folders, and estimating procedures. Those should be the starting point.

Deliverable: A standard project kickoff checklist and a clear handoff from estimating to project execution.

18

Process Priority: Purchasing, Changes, and Billing

Purchasing · Change orders · Progress billing · Project closeout

The next processes I would address are the ones that affect the financial picture of a project after work begins.

Purchasing

How does someone request materials or subcontractor services, obtain approval, document the purchase, and ensure the cost is associated with the correct job?

Change orders

Who identifies changes, determines the financial impact, obtains authorization, communicates with the customer, and makes sure the change is reflected in billing?

Progress billing

Who confirms work completed, prepares applications for payment, tracks retainage, and follows up on outstanding balances?

Project closeout

Who verifies that final invoices, costs, outstanding changes, and required documentation have been completed?

I'd establish short checklists and clear responsibilities for these activities, beginning with one or two active projects.

The goal is to determine which information needs to move between people and systems, and make that transfer consistent.

19

Clarifying Roles and Decision Authority

Understand the work and identify who is accountable for it, together.

One thing that became clear during our conversations is how much work is sitting with Aaron and Stuart.

During our November 13 meeting, Stuart raised a useful point: he wanted to understand the processes before deciding who should own them.

I agree that we need to understand the work before assigning responsibilities. We'll also need to identify the person accountable for each process as we're documenting it. I would approach those activities together.

For every major process, I'd want to know:

  • Who is responsible for completing the work?
  • Who is accountable for the outcome?
  • Who has authority to approve decisions or expenses?
  • When does an issue need to be escalated?
  • Who needs to be informed?

The resulting responsibility map should account for existing capabilities, workloads, and authority, including what work needs to move away from Aaron and Stuart.

I would begin with finance, project management, purchasing, estimating, billing, and administration.

20

A More Manageable Role for Stuart

More defined responsibility, clearer decision authority, and a consistent set of management tools.

Stuart is currently involved in project management, purchasing, subcontractor coordination, billing, accounting administration, and a substantial amount of day-to-day problem-solving.

He has demonstrated that he understands the business and is willing to ask questions when something doesn't make sense. I've also seen him raise practical concerns that are worth considering before committing the company to a decision.

I believe he would benefit from more defined responsibility, clearer decision authority, and a consistent set of management tools.

Some of what I would recommend includes:

  • A weekly project review with clear follow-up responsibilities.
  • A financial dashboard he can use without having to reconstruct information himself.
  • Spending and approval thresholds agreed upon with Aaron.
  • A consistent process for delegating and monitoring work.
  • Written expectations for the people supporting projects.
  • A way to evaluate operational problems before immediately stepping in to resolve them.

I can see Stuart continuing to grow into a more formal operational leadership role if that's what he and Aaron want.

Before expanding that role, though, we need to determine which existing tasks should be reassigned and what support he would need.

21

The Day 60 Review

Seven things I'd like to see in use by day 60.

By day 60, I'd like to see the following in use:

I would test these processes using actual projects and transactions.

If they require significant additional work, depend on one person being available, or aren't being followed, we should adjust them before introducing more.

Appendix C — Days 61–90: Reporting and Management
No tasks for this person in this phase.
22

What I'd Focus on During Month Three

Project profitability · Division performance · Capacity and workload · Cash and commitments · Operating processes

The third month is when I would begin putting the financial and operational information together to assess how the business is performing.

The timing of some of this will depend on the bookkeeper's progress.

I would prioritize:

Project profitability

Review estimated versus actual costs on a small number of active jobs, including the effect of overhead as the accounting information becomes available.

Division performance

Determine what revenue and expense reporting is possible for construction and masonry, and what would need to change to improve visibility.

Capacity and workload

Review who is managing active projects, what work is concentrated with particular people, and whether there are genuine staffing gaps.

Cash and commitments

Review the 13-week forecast against actual cash activity, upcoming projects, and known obligations.

Operating processes

Evaluate whether the processes introduced during the second month are being followed and whether they're improving the work.

23

The Management Dashboard I'd Recommend

Eight measures, from cash to capacity.

I would start with a manageable set of measures.

AreaWhat I'd want to see
CashCurrent cash and a 13-week forecast
ReceivablesOutstanding invoices, aging, and expected collection dates
PayablesBills and obligations coming due
Financial performanceRevenue, gross profit, overhead, and operating result
Job profitabilityEstimated and actual costs on selected projects
Project pipelineOpportunities, bids, expected awards, and likely start dates
Project executionActive jobs, owners, schedule risks, and major outstanding decisions
CapacityUpcoming work relative to available project and field resources

Some measures may still be unavailable or preliminary at day 90. We should label them accordingly.

The dashboard should help Aaron and Stuart determine what needs attention in the business each week and month, with the bookkeeper responsible for the accounting accuracy behind the financial reports.

24

Decisions I Would Revisit After 90 Days

Seven larger decisions to evaluate with better information.

Several larger decisions came up during our conversations.

They include:

  • Establishing separate legal entities for the operating divisions.
  • Defining Stuart's future leadership role and ownership arrangement.
  • Hiring additional field or project management support.
  • Expanding administrative and accounting capacity.
  • Developing the disaster and economic development division.
  • Changing or adding operational software.
  • Determining what outside leadership or consulting support the company can sustain.

Some legal or compliance matters may need to be addressed sooner, regardless of the timeline.

For discretionary investments, I recommend using the improving financial information and operational reporting to evaluate the options.

By the end of 90 days, we should have a better understanding of what support the business needs, what it can afford, and how additional people or systems would actually be used.

25

Where We Want to Be at Day 90

A much clearer picture of the business you're managing.

The goal is that, three months from now, Aaron and Stuart have a much clearer picture of the business they're managing.

I would expect the accounting cleanup to be making measurable progress, current financial activity to be following agreed procedures, and the most important project workflows to have assigned owners.

I'd also expect Stuart to have a more consistent way to review projects, delegate responsibilities, and bring decisions to Aaron, with fewer things depending on either of you having all the information in your head.

The financial information may still need work. Some processes will need to be adjusted. And the company may discover problems that weren't visible during this assessment.

That's part of why I want the roadmap to include reviews at days 30, 60, and 90. We should use what we learn to decide what happens next.

Part Three

Managing the work and deciding what comes next

26

A Working Management Rhythm

Weekly financial and project reviews, a monthly leadership review, and a roadmap review every 30 days.

I recommend beginning with a small number of recurring reviews.

FrequencyMeetingPurpose
WeeklyFinancial reviewCash, receivables, payables, upcoming obligations, and cleanup progress
WeeklyProject reviewActive jobs, upcoming milestones, staffing, changes, billing, and issues
MonthlyLeadership reviewFinancial performance, operational priorities, resource decisions, and progress against the roadmap
Every 30 daysRoadmap reviewConfirm what's complete, what needs attention, and what should happen next

These meetings should result in decisions and assigned responsibilities.

I would keep one shared action register with the task, responsible person, due date, and current status.

There's no need to create multiple dashboards and trackers if one will do the job.

Open the weekly review agenda →

27

Financial, Legal, and Compliance Matters

A few issues require professional review outside the operating assessment.

A few issues require professional review outside the operating assessment.

Tax filings and entity treatment

Confirm outstanding returns, legal entity status, and tax classification.

Historical liabilities

Review the older company's obligations, current payment arrangements, and any restrictions affecting financial or organizational decisions.

Payroll and worker classification

Confirm the treatment of workers, payroll taxes, and 1099 reporting with an appropriate professional.

Insurance, licensing, and bonding

Verify current requirements and any limitations affecting existing or prospective work.

Intercompany activity and future structure

Review how activity between entities is recorded and obtain appropriate guidance before changing the legal structure.

These items should be assigned to qualified professionals and tracked with the rest of the roadmap. I would not wait 90 days to address anything that is already time-sensitive.

28

My Recommendation for Continued Support

Invest first in establishing accurate financial information and the financial processes required to maintain it.

I've enjoyed getting to know the business and working with both of you through this assessment.

I believe there's more work we could accomplish together, particularly around Stuart's development as an operational leader, the implementation of the processes we've identified, and the way financial and operational reporting can inform your decisions.

I also want to be responsible in what I recommend.

I don't currently have the calendar capacity to take on an operational leadership or implementation role within Honoré. And given the condition of the financial records, I wouldn't feel comfortable recommending that you make a significant investment in a larger consulting engagement before we know what the business can support.

If it would be useful, one option is my Advise engagement at $5,500 per month, structured around biweekly coaching with Stuart and advisory support as the team implements this roadmap internally.

That could include reviewing decisions, identifying priorities, working through delegation and accountability challenges, and helping Stuart establish management practices that work for him and the business.

Any such engagement would require a separate agreement and confirmation of my availability. I am not currently committing to a December start.

You can also implement this plan with your existing team, bookkeeper, and other professionals.

At this stage, my recommendation is that you invest first in establishing accurate financial information and the financial processes required to maintain it.

Implementation Appendix

The working plan

The 30/60/90 action tables (Appendices A–C) live in the 90-day plan above. The rest of the working tools are here.

D

Appendix D — The Financial Responsibility Map

Proposed responsibilities to confirm with the team and bookkeeper

Proposed responsibilities to confirm with the team and bookkeeper

Highlight:
Financial activityDay-to-day responsibilityApproval or review

The final responsibilities should reflect the team's actual capacity and the services included in the local bookkeeper's agreement.

E

Appendix E — The Bookkeeper Scope Checklist

Check items off as you confirm them with the bookkeeper.

Before beginning the engagement, confirm:

F

Appendix F — How to Capture and Improve a Process

A practical process-development guide for Honoré's internal team, with a copy-and-paste AI prompt.

A practical process-development guide for Honoré's internal team, adapted from my Work in Practice method. This is intended to help you document what people are already doing, decide what needs to change, and give the next person a way to do the work without relying entirely on someone's memory.

Begin with something specific. I would start with the purchasing/receipt handoff into accounting, followed by the handoff from an awarded project to the person managing the job. Both affect the financial work already underway.

1. Decide what the problem actually needs

Before writing an SOP, ask whether the issue is a missing instruction, an easy-to-miss checklist item, an unclear approval, a tool that isn't configured well, or a step that no longer needs to happen. A short checklist or a clearer decision authority may be enough. Don't document unnecessary work just because it's what has always happened.

2. Interview each other about one real example

Have the person who does the work explain it to someone who needs to understand it. If everyone agrees, record the conversation and transcribe it; otherwise, take detailed notes. Use an actual recent purchase or project rather than describing how the process should ideally work.

  • What started the work? Who was involved, and what did each person actually do?
  • Which tools, files, forms, or accounts were used? Where did the information go next?
  • What required approval? What did you do when something was missing or unexpected?
  • Where did someone have to chase information, repeat a step, or fix something?
  • How did you know the work was complete? What would you change the next time?

3. Use AI to organize a first draft

Use the transcript or interview notes with the prompt below. AI can help organize the sequence and identify missing information, but the person doing the work needs to verify every step. Don't upload sensitive banking, customer, payroll, or employee information into a tool the company hasn't approved for that use.

Copy-and-paste AI prompt

Help us document one internal process at Honoré Holdings using the attached interview transcript and any approved reference material. First, tell us whether this work needs detailed instructions, a short working checklist, a decision guide, clearer approval authority, a change to an existing tool, or fewer steps. Explain your recommendation briefly.

Then draft: (1) a plain-language process with its purpose, starting trigger, accountable owner by role, people involved, required information, steps in order, approvals, handoffs, exceptions, and what must be true when it is complete; (2) a short checklist someone can actually use while doing or checking the work, if appropriate; (3) the specific questions we still need to answer; and (4) a plan to test this on the next real occurrence.

Separate what people said they do today from any proposed improvements. Do not invent names, approval limits, system settings, cost codes, or accounting rules. Mark missing information as TO CONFIRM. Use language the team would actually use. We will review and approve the draft before using it.

4. Check it with the people who do the work

Have the interviewer and the person who performs the process read the draft together. Confirm the sequence, ownership, approvals, and systems. If it affects accounting, the bookkeeper should confirm the relevant documentation and job-coding requirements. Assign one process owner, even when several people perform different steps.

5. Use it, then change what did not work

Follow the process the next time the work comes up. Notice where someone needs to ask a question, where a step is missing, and where the instructions create unnecessary work. Update the document while the experience is fresh. The first version is a starting point; it becomes useful through actual use.

Keep the final version simple

Every approved process should identify its owner, when to use it, the necessary steps or checklist, decision/approval points, exceptions, where the record lives, and when it was last updated. Save it in the existing shared project or operations library, not in a new system. Review it again after a few uses or when something materially changes.

Recording and AI-use note: Ask participants before recording. Use company-approved tools and remove sensitive information before uploading transcripts. A human process owner must approve changes. AI-generated drafts are not a substitute for the bookkeeper's or another qualified professional's judgment on financial, legal, tax, safety, or compliance matters.

Adapted for Honoré Holdings from the Work in Practice Process Development Framework. Provided for Honoré's internal use; please do not distribute or publish this guide without permission.

G

Appendix G — Weekly Management Review

Financial review (30 min) · Project review (30 min) · Monthly leadership review (60 min)

Financial review, 30 minutes

  • Current cash and upcoming obligations.
  • Receivables and collections.
  • Payables and payments due.
  • Accounting cleanup progress.
  • Missing documentation or unresolved transactions.
  • Decisions requiring Aaron's attention.

Project review, 30 minutes

  • Active project status.
  • Upcoming milestones and material requirements.
  • Staffing and subcontractor coordination.
  • Change orders and billing.
  • Issues requiring approval or escalation.
  • Assignments for the coming week.

Monthly leadership review, 60 minutes

  • Available financial performance.
  • Cash forecast and obligations.
  • Project performance.
  • Progress against the 30/60/90-day roadmap.
  • Resource and staffing decisions.
  • Priorities for the following month.

Record decisions, accountable owners, and due dates in one shared register.

H

Appendix H — Outstanding Verification and Professional Review

Ten items to keep visible until resolved. Set a status for each.

AreaWhat still needs confirmationResponsible partyStatus

These items should remain visible in the management action register until resolved. Any time-sensitive compliance or legal matter should be addressed immediately, regardless of its position in the 90-day plan.

Final Note

I've tried to make recommendations that reflect the business you described to me, including the resources you have available today and the uncertainty around the financial position.

There is work here that will require outside expertise, particularly in accounting, and there are operating changes that Aaron, Stuart, and the existing team can begin making without a substantial additional investment.

I would begin with the financial work, establish the first set of procedures, and review what we learn at the end of 30 days. That will give us a better basis for determining what comes next, including how much additional support the business actually needs and can afford.

Brittany MartinManaging Partner, Instar Partners